Hummingbird

Hummingbird

Recurrent Energy is developing the Hummingbird Solar Project, a solar + battery energy storage facility in Fleming County, KY. The project is anticipated to be 200 MWac solar and up to 200 MW/800 MWh of storage. The Hummingbird Solar land position consists of approximately 2,066 acres, with approximately 1,638 expected to be utilized for solar equipment in the current design.

Project Details
LocationFleming County, Kentucky, United States
Project Capacity200 MWp solar + up to 200 MW/800 MWh storage
Homes PoweredApproxiately 34,000 homes annually
Targeted Operation Date12/31/2024
AcreageApproximately 2,066 acres with approximately 1,638 acres to be utilized for solar equipment in the current design
InterconnectionA new substation on the Goddard to Plumville 138 kV line
CustomerTBD
Est. Jobs CreatedApproximately 350 for construction and 3-5 jobs during the operation period
Estimated TaxesTBD
Earliest Construction Start Date9/30/2023
FAQs
How much land will be needed for the Hummingbird Solar Project?

The Hummingbird Solar land position consists of approximately 2,066 acres, with approximately 1,638 expected to be utilized for solar equipment in the current design. Fleming County comprises over 224,600 acres of land, so the project area will account for less than 1% of Fleming County’s total acreage yet will generate enough energy to power 34,000 homes annually. The Hummingbird Solar Project will generate millions of dollars of long-term additional revenue to Fleming County over the project’s anticipated operational life. The significant tax increase will improve local schools, emergency services, and other infrastructure improvements.

Do solar projects make economic sense?

In the last decade, the cost to install solar has dropped by more than 70%, and as of Q4 2020, prices are at their lowest historical level across all market segments. Due to continuing technological innovations, new utility-scale solar energy projects are now often cost-competitive with new natural gas generation. In fact, new solar projects are often cheaper than both coal and natural gas. Because solar PV is a technology and not a fuel (like oil, gas and coal), costs will continue to decline as research continues to improve existing technology.

Are solar panels safe?

Because the photovoltaic (PV) panel materials are enclosed and do not mix with water or vaporize into the air, there is little-to-no risk of chemicals, including greenhouse gasses, being released into the environment during normal use. Crystalline silicon PV panels, which are extremely common and used worldwide, “do not pose a material risk of toxicity to public health and safety.”

All solar facilities are designed to strict electrical safety standards to ensure safe operation. Product safety standards, installation requirements, and building codes for solar facilities are addressed by the National Fire Protection Agency’s National Electric code, the International Code Council’s International Fire Code, the International Association of Firefighters, and several other safety product and standards groups.

What steps will you take to prevent trespassing in the project area?  

The National Electric Code requires appropriate levels of warning on all electrical components. The Hummingbird Solar Project will be surrounded by a fence at least six feet in height in accordance with the Fleming County Code, with three strands of barbed wire on top as an added protection measure. Along with the security fencing, the vegetative buffer will also deter trespassers.

Will glint or glare from sunlight be an issue?

Glint refers to the direct reflection of the sun on a solar panel. Glare is a continuing source of brightness, not the direct reflection of the sun. Solar arrays are designed to absorb light and produce electricity, not reflect it. The panels that we will use for the Hummingbird Solar Project have an anti-reflective coating, which helps to increase the amount of light absorbed into the cell, thereby increasing efficiency and reducing glare and allowing the panels to blend in more easily with the surrounding area. If the project site is near an airport, we are required to submit a filing to the FAA, at which point it will be determined if a glare study needs to be conducted. Moreover, the landscaping around the perimeter of the project will buffer any glint and glare that may be produced.

How frequently will the property be monitored?  

The Hummingbird Solar Project will be monitored during operating hours by onsite staff. The entire property will also be monitored remotely 24 hours a day, 7 days a week.

Will the Hummingbird Solar Project affect my property value?

Examining property values across the United States demonstrates that large-scale solar projects like the Hummingbird Solar Project have no measurable impact on the value of the adjacent properties, and in some cases, may even have positive effects. Studies also show that proximity to solar projects does not deter the sales of agricultural or residential land.

How will the vegetation within the property be maintained?

Maintenance crews will maintain the perimeter and interior landscaping within the project boundaries. The interior ground cover shall not exceed 18 inches, with a typical maximum height of 12 inches, so that it doesn’t interfere with the panels or other electrical components.

Are solar projects good for the environment?

While producing electricity with photovoltaics emits no pollution, produces no greenhouse gas emissions, and uses no finite fossil fuel resources, it has been argued that solar power has a hidden carbon footprint due to solar panel manufacturing and project construction. Both fossil fuel and non-fossil fuel power technologies induce life-cycle greenhouse emissions that stem from the energy requirements for their construction and operation. Known as a “carbon debt,” this debt of energy must be paid off to calculate how solar projects reduce emissions over their lifetime. A typical utility-scale solar project—like the Hummingbird Solar Project—repays its carbon footprint in roughly 12 months or less, providing decades of zero emission energy.

How will this project affect Fleming County wildlife?

When sited and developed properly, the installation of a solar facility will have minimal impacts on wildlife in the area. In fact, studies show that solar facilities can provide shelter for species, promote land stability, preserve habitat, and support biodiversity.

A natural resource assessment will be conducted on the Hummingbird Solar Project site to determine presence, if any, of federally or state listed species and critical habitat.  Special species surveys will occur as necessary.

Once constructed, solar projects produce no pollution, emissions, or noise. Further, vegetation can grow under the panels, and solar facilities can provide sanctuaries for flora and fauna to thrive.

Limited fencing will be erected around panel areas as a security measure in accordance with industry best practices and local requirements. However, waterways in the project area will not be fenced to allow continued wildlife access to the water resource.

What are you doing to protect the wetlands?

A wetland delineation will be performed on the Hummingbird Solar Project site. Coordination with U.S. Army Corps of Engineers will occur to determine if features identified on site are jurisdictional. The project will maintain at least a 25-foot setback from all identified, jurisdictional features.  As project design is finalized, if impacts to waters on site cannot be avoided, appropriate permits will be secured.

Will leakage occur?

The construction of the Hummingbird Solar Project will not require toxic chemicals or processes. Photovoltaic (PV) panels typically consist of glass, aluminum, copper, silver, and semiconductor materials that can be successfully recovered and reused. Because the PV panel materials are enclosed and do not mix with water or vaporize into the air, there is little-to-no risk of chemicals, including greenhouse gases, being released into the environment during normal use. Crystalline silicon PV panels, an extremely common panel variant used around the world, “do not pose a material risk of toxicity to public health and safety.

In addition, to provide decades of corrosion-free operation, panels like the ones that will be used for the Hummingbird Solar Project, are encapsulated from air and moisture between two layers of plastic. The encapsulation layers are further protected with a layer of tempered glass on the front and a polymer sheet on the back. For decades, this same material has been used between layers of tempered glass to give car windshields and hurricane windows their great strength, allowing them to stay intact even if damage occurs.

What happens to the rain when it hits the panels?

The Hummingbird Solar Project will use a solar panel tracking system, allowing the reflective surfaces to align with the sun as it moves across the sky. Therefore, due to continuous tilt, water will not collect on the panels during rainstorms. The rainwater that runs off the panels is absorbed into the ground, nurturing the groundcover. Any excess rainwater leaves the site as stormwater runoff, just as it does now.

How will the panels be washed? Will you use ground water?

Due to the average amount of rainfall Fleming County normally experiences, we do not anticipate regularly scheduled washing of the panels. However, if washing is required, distilled water is used because ground water can leave a film or deposits on the panels.  No chemicals or solvents will be used during the panel cleaning process.

How will decommissioning work?

The Hummingbird Solar Project will submit a detailed decommissioning plan and cost estimate prior to the issuance of a Building Permit. These plans have given elected officials throughout Kentucky and the nation confidence in approving these long-term infrastructure projects. Decommissioning will include removal of all non-utility owned above ground equipment, transformer, inverters, conduit stub outs, or other above ground structures including foundations. At the end of the project’s operational life, the land can be returned to its prior natural condition.

Can solar panels be recycled?

Photovoltaic (solar) panels typically consist of glass, aluminum, copper, silver and semiconductor materials than can be successfully recovered and reused at the end of their useful life. Alternatively, solar PV components can be reused or refurbished to have a “second life” of generating electricity.

What provisions will be made to guarantee that the funds are in place when it is time to decommission the facility?

The Hummingbird Solar Project will post financial security to cover the full cost of decommissioning at the end of the Project’s life. This financial assurance must be in place before construction begins.

Can the land return to agricultural use after decommissioning?

Solar projects are low impact and coexist well with agriculture, operating without any impact to adjacent agricultural properties. A solar project’s lifespan allows the soil in the project area to rest and replenish nutrients. Native vegetation can grow under the panels, allowing the land to retain water and topsoil, improving soil health over time. After decommissioning occurs at the end of the Project’s life, the land can revert back to its previous agricultural use.

Will concrete be used around the piles holding up the panels? 

There will be no concrete poured around piles holding up tracker rows. There will be limited amounts of concrete for inverter pads and at the substation.

What will you do to maintain traffic safety during construction and once the site is running?

The Hummingbird Solar Project will be designed in accordance with Kentucky Transportation Cabinet safety guidelines. Signage and flagging will be implemented during construction as required. After construction is complete, the daily traffic will be reduced to one or two standard-size vehicles.

What is the anticipated regular construction schedule? 

We anticipate that the Hummingbird Solar Project will have a 15-month construction timeline. Construction will only occur during daylight hours Monday-Friday, and some work may occur on Saturdays. We do not anticipate construction activities taking place on Sundays.

What will you do to protect the topsoil from being depleted during construction?

The Hummingbird Solar Project will use construction methods that minimize large-scale grading and removal of native soil. Minor grading may be needed, but we take the conservation of topsoil very seriously. Typical construction practices require that topsoil be excavated and preserved onsite prior to performing cut/fill operations. The preserved topsoil will be redistributed across the graded areas to assist in growing adequate ground cover as quickly as possible to provide ground stabilization. The site cut and fill will be appropriately balanced, with no anticipation of import/export necessary.

Questions

Project Contact Info: (859) 694-2777

hummingbird@recurrentenergy.com

Recurrent Energy Announces $500 Million Capital Commitment from BlackRock

The investment will provide Recurrent Energy with additional capital to grow its high value project development pipeline while executing its strategy to transition from a pure developer to a developer plus long-term owner and operator in select markets including the U.S. and Europe.